A major reconstruction of the runway intersection is due to be carried out at Warsaw Chopin Airport in September 2010. As a result, only the shortened runway section of 1300m will be available for operations in the first three weekends of September. The shorter runway section will facilitate movements of small passenger aircraft only.
Temporary closure of Chopin Airport in September 2010
Schedule of the runway intersection reconstruction works
From 3 September, 23:30h to 6 September, 05:00h
From 10 September, 23:30h to 12 September, 08:00h
From 17 September, 23:30h to 19 September 08:00h
* plus the night before and after
During the works at the intersection, the shortened runway section will be available for small aircraft between 5:00 - 23:00 h.
Temporary closure of Chopin Airport in September 2010
Schedule of the runway intersection reconstruction works
From 3 September, 23:30h to 6 September, 05:00h
From 10 September, 23:30h to 12 September, 08:00h
From 17 September, 23:30h to 19 September 08:00h
* plus the night before and after
During the works at the intersection, the shortened runway section will be available for small aircraft between 5:00 - 23:00 h.